alex, what we have been doing is maintenance on callbacks no matter what route you are on, it is the only way we can keep each other off the radar so ...

13 years ago
Reply

cleaning pits one day, was taking an old corn broom to the trash when the building maintenance supervisor asked me if i was riding that home???? bit m...

13 years ago
Reply

i make a s&it ton of money form the new guy going on calls and shutting down elevators, telling the boss what is wrong and then i go in a fix it t...

13 years ago
Reply

i bet not!!!!

13 years ago
Reply

no one covers anything, i can't tell you how many times this year i was the only guy working on a Friday because everyone wanted it off.

13 years ago
Topic
13 years ago
Replies: 12
Views: 13633
Reply

get some CAT OIL or Metalcoat, its an additive you put in the oil it works wonders!!!!! yes that is CAT as in Caterpillar machinery

13 years ago
Reply

have had contracts the covered rebuilding parts if possible or if obsolete.

13 years ago
Reply

might i add one more reason to get rid of this thing before someone gets hurt....single bottom jack!!!

13 years ago
Topic
13 years ago
Replies: 1
Views: 2975
Reply

derick i know i can disable it but the way the have the wiring for the new code i would have no protection. so far no call back after the PSB swap

13 years ago
Reply

i have been off for a few days i will see if anything has come up after the PSB swap, i will keep posted

13 years ago
Reply

building owners should not be working on elevators

13 years ago
Reply

LOS tripped again, replaced the power supply board (PSB) found a bad R3 resistor. see if this does anything

13 years ago
Reply

job is only 6 months old so there is little chance of contamination that i would know of unless something was in the jacks, it is a holeless system. g...

13 years ago